Inspection Report about Heating and Vacuum System, Bathrooms, and Buildings

Date
September 13, 1911

Supervisor of Construction John Charles provides a report on the heating system and buildings at the Carlisle Indian School. He writes about completing the heating and vacuum system, the newly renovated guardhouse, building a workshop for the engineer, building new bathrooms for the dormitories, installing manholes for the sewer system, and he provides a report on the shops and shop instructors. Charles estimates that $28,000 is needed to fulfill all of his recommendations.

Time Period
Year
People
Standard Forms & Transactions
Repository
National Archives and Records Administration
Location
RG 75, CCF Entry 121, #85084.1-1911-Carlisle-410
Inspection Report about Heating and Vacuum System, Bathrooms, and Buildings